AI- 45918
Purchasing Department 9.B.
CC CONSENT
- Meeting Date:
- 08/12/2014
- Submitted For:
- Comm. J Palacios, HC Pct. #4
- Submitted By:
- Letty Saenz, PURCHASING DEPT.
- Department:
- PURCHASING DEPT.
Information
CAPTION
1. Acceptance and approval of SUPPLEMENTAL AGREEMENT No. 1 to extend the term of current Professional Engineering Services Agreement # C-13-178-08-20, until completion of the scopes under Exhibit B (Scope of Services) submitted by L & G ENGINEERING for the purposes of "engineering services" for: FM 2220 (Ware Road Project) within Hidalgo County Precinct No. 4, to expire August 19, 2016.
2. Acceptance and approval of WORK AUTHORIZATION No. 6 in the amount of ($ 49,207.32) submitted by L&G ENGINEERING LABORATORY contracted engineering firm for "professional laboratory services" or (On Call) “Geo Technical & Construction Materials Testing Services” for projects located within Hidalgo County Precinct #4, under Contract# C-13-220-08-13 - PROJECT: (CONSTRUCTION MATERIAL TESTING SERVICES) - LINN-SAN MANUEL EMERGENCY FACILITY PROJECT IN PRECINCT 4 (a project carried by, MATA-GARCIA ARCHITECTS & CONTRACTED CONSTRUCTION COMPANY - J-CON CONSTRUCTION, LLC).
2. Acceptance and approval of WORK AUTHORIZATION No. 6 in the amount of ($ 49,207.32) submitted by L&G ENGINEERING LABORATORY contracted engineering firm for "professional laboratory services" or (On Call) “Geo Technical & Construction Materials Testing Services” for projects located within Hidalgo County Precinct #4, under Contract# C-13-220-08-13 - PROJECT: (CONSTRUCTION MATERIAL TESTING SERVICES) - LINN-SAN MANUEL EMERGENCY FACILITY PROJECT IN PRECINCT 4 (a project carried by, MATA-GARCIA ARCHITECTS & CONTRACTED CONSTRUCTION COMPANY - J-CON CONSTRUCTION, LLC).
BACKGROUND
Supplemental Agreement #1 to Prof Svcs Agreement # C-13-178-08-20 - L&G Engineering
Work Authorization # 6 - Linn-San Manuel Project - C-13-220-08-13 - L&G Engineering Laboratory
Work Authorization # 6 - Linn-San Manuel Project - C-13-220-08-13 - L&G Engineering Laboratory
Fiscal Impact
- FISCAL YEAR:
- 2014
- ACCT. #:
- 4-1315-431-00-124-135-0-841
- FUNDS AVAILABLE Y/N?:
- Y
- MATCHING FUNDS Y/N?:
- N
BUDGETARY IMPACT:
PO#696996- FISCAL YEAR:
- 2014
- ACCT. #:
- 4-1301-419-40-124-136-0-720
- FUNDS AVAILABLE Y/N?:
- y/pending
- MATCHING FUNDS Y/N?:
- n
BUDGETARY IMPACT:
***Budgetary impact for WA#6 - L&G Engineering (CMT) Linn San Manuel Project to be provided by Precinct 4 staff. Funding available pending cc approval of AI45860, followed by an emergency transfer into approp. acct.Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | msalazar | 08/08/2014 03:28 PM |
| Budget and Management | Debbie Tamez | 08/08/2014 04:07 PM |
| Auditor's Office | Monica Salinas | 08/08/2014 05:20 PM |
- Form Started By:
- Letty Saenz
- Started On:
- 08/07/2014 05:11 PM
- Final Approval Date:
- 08/08/2014