CAPTION

Acceptance and approval of Change Order No. 4 for an extension of sixty (60) days and zero additional dollars to Contract No. C-13-072A-11-19 with Couric Enterprises, LLC dba Foremost Construction as reviewed/approved by project architect of record, Mata-Garcia Architects, LLP for: Hidalgo County Precinct No. 4 -"Construction of a Community Resource Center in San Carlos" with authority for County Judge, or Court Member to execute document. 

BACKGROUND

CHANGE ORDER #2 - FOREMOST CONSTRUCTION

Fiscal Impact

FISCAL YEAR:
2014
ACCT. #:
4-1342-419-40-124-123-0-720
FUNDS AVAILABLE Y/N?:
Y
MATCHING FUNDS Y/N?:
N

BUDGETARY IMPACT:

Original P.O. # 703489

Attachments

Form Review

Inbox Reviewed By Date
Purchasing / Internal msalazar 01/16/2015 09:42 AM
Budget and Management Veronica Ortiz 01/16/2015 09:45 AM
Auditor's Office Monica Salinas 01/16/2015 06:31 PM
Form Started By:
moysalazar
Started On:
01/14/2015 03:52 PM
Final Approval Date:
01/16/2015