CAPTION
Presentation for consideration, discussion acceptance and approval of Change Order No. 1 in the amount of $6,989.50 (increase) for material and work adjustments as submitted by contractor, Sascon, Inc. and as recommended by project engineer TEDSI Infrastructure for "La Blanca Heights Subdivision" C-CAP-07-017-05-01 through the Border Colonia Access Program Project(s).
BACKGROUND
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | msalazar | 08/03/2007 01:22 PM |
| Budget and Management | Damaris San Miguel | 08/03/2007 04:30 PM |
| Auditor's Office | 08/03/2007 04:57 PM |
- Form Started By:
- lmoya
- Started On:
- 08/01/2007 03:43 PM
- Final Approval Date:
- 08/03/2007