CAPTION
1. Requesting exemption from competitive bidding requirements under the Texas Local Government Code 262.024 (a)(4) for construction material testing services.
2. Presentation of the scoring grid for the purpose of ranking by Commissioner’s Court of at least three (3) construction material testing firms from the county’s approved “pool” as graded and evaluated by the City of Progreso, Urban County Program, and Hidalgo County Purchasing Department, in connection with and funded through Hidalgo County Urban County Program Years 26, 27 & 28 (2013, 2014 & 2015) City of Progreso – Street Improvements funds.
3. Authority to negotiate a construction material testing service contract with the highest ranked firm ________________________________________ for a Urban County Program Years 26, 27 & 28 (2013, 2014 & 2015) City of Progreso – Street Improvements project.
2. Presentation of the scoring grid for the purpose of ranking by Commissioner’s Court of at least three (3) construction material testing firms from the county’s approved “pool” as graded and evaluated by the City of Progreso, Urban County Program, and Hidalgo County Purchasing Department, in connection with and funded through Hidalgo County Urban County Program Years 26, 27 & 28 (2013, 2014 & 2015) City of Progreso – Street Improvements funds.
| Professional Service Firm | Grade | Ranked |
| Raba Kistner Consultants | 94% | |
| Terracon | 88.33% | |
| Millennium Engineers Group | 87.33% |
3. Authority to negotiate a construction material testing service contract with the highest ranked firm ________________________________________ for a Urban County Program Years 26, 27 & 28 (2013, 2014 & 2015) City of Progreso – Street Improvements project.
BACKGROUND
Testing will be conducted on streets identified in Years 26, 27 & 28 (2013, 2014 & 2015) workplans.
Funds Available: $225,220.60 YR 28 (2015) Street Improvements
Funds Available: $225,220.60 YR 28 (2015) Street Improvements
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Budget and Management | Veronica Ortiz | 11/24/2015 04:19 PM |
| Purchasing / Internal | Monica Salinas | 11/25/2015 03:08 PM |
- Form Started By:
- olerma
- Started On:
- 11/24/2015 02:52 PM
- Final Approval Date:
- 11/25/2015