AI- 55591
Purchasing Department 20.F.1.
CC - REGULAR
- Meeting Date:
- 08/16/2016
- Submitted For:
- Marty Salazar
- Submitted By:
- Yvette Salinas, PURCHASING DEPT.
- Department:
- PURCHASING DEPT.
Information
CAPTION
Acceptance and approval of the following for “Construction of Space Pressure Control at Autopsy Facility" C-16-238-07-19 between Hidalgo County and Herrcon, LLC as submitted through project engineer Halff Associates, Inc. and as approved as to form by HC-DAs Office, Civil Service attorney :
A. Final construction contract (CC award 07-19-16/AI# 55383) in the amount of $82,500.00 with Herrcon, LLC;
B. Pursuant to TXLGC 262.031 and in the interest of expediting a project's progress, requesting authority/approval for the Executive Officer, Valde Guerra unless other designee to execute change orders that involve ...'an increase or decrease in cost of $50,000.00 or LESS...'. The original contract price may not be increased by 18 % or more without the consent of the contractor".
BACKGROUND
Contract subject to final legal review
Fiscal Impact
- FISCAL YEAR:
- ACCT. #:
- 6-1100-419-40-220-045-0-452
- FUNDS AVAILABLE Y/N?:
- y
- MATCHING FUNDS Y/N?:
- n
BUDGETARY IMPACT:
req# 304023 Funds available as 8/12/2016.Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | msalazar | 08/12/2016 03:44 PM |
| Budget and Management | Veronica Ortiz | 08/12/2016 03:47 PM |
| Final Approval | Monica Salinas | 08/12/2016 05:55 PM |
- Form Started By:
- yislas
- Started On:
- 07/27/2016 11:35 AM
- Final Approval Date:
- 08/12/2016