CAPTION
A. Clarification on AI #57367 as presented on CC 12/06/2016 to correct Change Order No. 2 with a cost decrease of ($30,326.40) and to extend the term an additional one (1) day in connection with C-16-120-05-10 - Hidalgo County Precinct No 4 - Mile 17.5 Road Paving & Drainage Improvements as recommended by project engineer Jose Noe Saldivar, P.E.;
B. Presentation for approval of "Certificate of Substantial Completion" reflecting the date of September 20, 2016 by Texas Cordia Construction. LLC contracted vendor for Mile 17.5 Road Paving & Drainage Improvements as submitted through project engineer Jose Noe Saldivar, P.E.
C. Approval of "Certificate of Construction Completion" as submitted by Texas Cordia Construction, LLC., reflecting the date of September 21, 2016.
B. Presentation for approval of "Certificate of Substantial Completion" reflecting the date of September 20, 2016 by Texas Cordia Construction. LLC contracted vendor for Mile 17.5 Road Paving & Drainage Improvements as submitted through project engineer Jose Noe Saldivar, P.E.
C. Approval of "Certificate of Construction Completion" as submitted by Texas Cordia Construction, LLC., reflecting the date of September 21, 2016.
BACKGROUND
Fiscal Impact
- FISCAL YEAR:
- 2016
- ACCT. #:
- 6-1200-431-00-124-142-0-721/841
- FUNDS AVAILABLE Y/N?:
- Y
- MATCHING FUNDS Y/N?:
BUDGETARY IMPACT:
PO #744580 for Texas Cordia Construction, LLC; funds available as of 1-4-17.Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | msalazar | 01/03/2017 11:11 AM |
| Budget and Management | Veronica Ortiz | 01/03/2017 11:55 AM |
| Final Approval | Monica Salinas | 01/06/2017 05:49 PM |