CAPTION
J-09 Drain Improvements Phase II: Change Order No. 3 increase in the amount of $7,490.40 for Contract No. HCDD1-16-006-04-26, Texas Cordia Construction reviewed and approved by Raul E. Sesin, P.E. CFM; District General Manager.
BACKGROUND
Fiscal Impact
Attachments
No file(s) attached.
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Monica Salinas | 01/20/2017 05:46 PM |
- Form Started By:
- Jaime Salazar
- Started On:
- 01/19/2017 06:08 PM
- Final Approval Date: