CAPTION

Acceptance and approval of Change Order No. 2 to [extend the term an additional twenty-six (26) days] in connection to agreement #C-16-145A-07-19 with RG Enterprises, LLC. dba, G&G Construction as [reviewed/recommended by project architect Mata-Garcia Architects, LLP] for ongoing project: "Landscape/Structural and Irrigation Construction for the San Carlos CRC" in Precinct 4.

BACKGROUND

Change Order #2-G&G Contractors, LLC
 

Fiscal Impact

FISCAL YEAR:
2017
ACCT. #:
7-1345-419-40-124-123-0-740
FUNDS AVAILABLE Y/N?:
MATCHING FUNDS Y/N?:

BUDGETARY IMPACT:

PO No. 748664

Attachments

Form Review

Inbox Reviewed By Date
Purchasing / Internal msalazar 03/29/2017 02:59 PM
Budget and Management Veronica Ortiz 03/29/2017 04:10 PM
Final Approval Monica Salinas 03/31/2017 05:51 PM
Form Started By:
Letty Saenz
Started On:
03/28/2017 10:35 AM
Final Approval Date:
03/31/2017