AI- 59177
Purchasing Department 22.D.2.
CC - REGULAR
- Meeting Date:
- 04/05/2017
- Submitted For:
- Norma Ceballos
- Submitted By:
- Norma Ceballos, COMM. PCT. #3
- Department:
- COMM. PCT. #3
Information
CAPTION
Acceptance and approval of Work Authorization No. 3 (with an estimated amount cost of $247,600.00) as submitted by project engineer, L&G Consulting Engineers, Inc. to provide Engineering Services required for the preparation of the Phase III Right-of-Way Map for the Mile 3 project from FM 492 to Tom Gill and the Design of Outfall Structures and Connections at the Intersection of Abram Road and Mile 3.
BACKGROUND
Funding - Agenda AI-59176
Fiscal Impact
- FISCAL YEAR:
- 2017
- ACCT. #:
- 7-1347-431-00-123-051-0-841
- FUNDS AVAILABLE Y/N?:
- Y/pending
- MATCHING FUNDS Y/N?:
- N
BUDGETARY IMPACT:
Funds available pending cc approval of AI #59176Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | msalazar | 03/31/2017 01:28 PM |
| Budget and Management | Veronica Ortiz | 03/31/2017 02:41 PM |
| Merlen P. Munoz | mmunoz | 03/31/2017 04:49 PM |
| Final Approval | Monica Salinas | 03/31/2017 05:51 PM |
- Form Started By:
- nceballos
- Started On:
- 03/30/2017 02:35 PM
- Final Approval Date:
- 03/31/2017