CAPTION

Ratification of fully executed Change Order No. 2 reflecting an additional 59 calendar days to contractor RDH Site & Concrete Co., due to rain days and days too wet to work, for Pct. 1 Goolie Rd Paving Improvements Project as submitted though project engineer, LeFevre Engineering & Management Consulting, LLC (C-16-277-08-09) subject to compliance to HB1295 & HB23 if and when applicable.

BACKGROUND


Fiscal Impact

CALENDAR YEAR:
2017
ACCT. #:
7-1XX0-431-XX-121-XXX-X-721
FUNDS AVAILABLE Y/N?:
MATCHING FUNDS Y/N?:

BUDGETARY IMPACT:

no fiscal impact, increase of work days only.

Attachments

Form Review

Inbox Reviewed By Date
Purchasing / Internal msalazar 04/11/2017 09:09 AM
Budget and Management Veronica Ortiz 04/11/2017 09:16 AM
Merlen P. Munoz mmunoz 04/11/2017 09:39 AM
Final Approval Monica Salinas 04/13/2017 04:27 PM
Form Started By:
yislas
Started On:
04/07/2017 05:03 PM
Final Approval Date:
04/13/2017