1. Certificate of Construction Completion as submitted by 2GS,LLC. reflecting the date of 1/8/17 for Paving & Drainage Improvements for Colonia Noreste Project
2. Application for Pmt.# 5 Retainage Release in the amount of $28,009.38 as submitted by 2GS,LLC - Contract# C-16-260-07-19 under PO# 749711 for the provision of Paving & Drainage Improvements for Colonia Noreste.
2. Application for Pmt.# 5 Retainage Release in the amount of $28,009.38 as submitted by 2GS,LLC - Contract# C-16-260-07-19 under PO# 749711 for the provision of Paving & Drainage Improvements for Colonia Noreste.
BACKGROUND
Fiscal Impact
- CALENDAR YEAR:
- 2017
- ACCT. #:
- 7-1350-431-00-121-211-0-721
- FUNDS AVAILABLE Y/N?:
- Y
- MATCHING FUNDS Y/N?:
BUDGETARY IMPACT:
PO# 749711Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Monica Salinas | 04/13/2017 04:27 PM |
- Form Started By:
- ndelosrios
- Started On:
- 04/13/2017 02:31 PM
- Final Approval Date:
- 04/13/2017