Skip to main content

AgendaQuick™

View Agenda Item

AI- 59444
Purchasing Department   11.C.
CC CONSENT
Meeting Date:
04/18/2017
Submitted For:
David Fuentes
Submitted By:
Amy Saenz-Smith, COMM. PCT. #1
Department:
COMM. PCT. #1

Information

CAPTION

1. Ratification for change order No. 2 was approved by precinct to increase quantities on site 7 and decrease quantities on site 9 in the amount of $44,588.68 with no change to contract amount;
2. Approval of Payment Application No. 3 in the amount of $87,754.65 submitted by Bearkat Construction LLC, awarded contractor for Precinct 1's Mile 9 North Road FEMA Project as certified for payment by project engineer, TEDSI Infrastructure Group, C-16-290-09-06.

BACKGROUND

FEMA

Fiscal Impact

CALENDAR YEAR:
2017
ACCT. #:
7-1280-431-00-121-80X-5-721
FUNDS AVAILABLE Y/N?:
Y
MATCHING FUNDS Y/N?:

BUDGETARY IMPACT:

Funds available through PO751893

Attachments

Form Review

Inbox Reviewed By Date
Purchasing / Internal msalazar 04/13/2017 03:48 PM
Budget and Management Veronica Ortiz 04/13/2017 03:51 PM
Final Approval Monica Salinas 04/13/2017 04:27 PM
Form Started By:
asaenz
Started On:
04/13/2017 03:34 PM
Final Approval Date:
04/13/2017