DRAINAGE - CONSENT
Meeting Date:
10/24/2017
Submitted For:
Raul Sesin
Submitted By:
Lora Briones, DRAINAGE DISTRICT
Department:
DRAINAGE DISTRICT

Information

CAPTION

A.  2013 Bond Projects - Lucero del Norte, Precinct #1 Rural Drainage Development.   Approval of Change Order No.1,  to add 27 more contract days.  Contractor is Texas Cordia and the Engineer is Urban Infrastructure Group.
 
B.  2013 Bond Projects - Lucero del Norte, Precinct #1 - Rural Drainage Development.  Approval of Change Order No. 2 ,  to increase the amount of the contract by $6,798.80.  Contractor is Texas Cordia Construction and the Engineer is Urban Infrastructure Group.