DRAINAGE - CONSENT
- Meeting Date:
- 11/07/2017
- Submitted For:
- Jaime Salazar
- Submitted By:
- Moises Salazar, DRAINAGE DISTRICT
- Department:
- DRAINAGE DISTRICT
Information
CAPTION
Ratification of the fully executed Change Orders No. 2 & 3, reflecting a net increase of $1,625.00 for mail boxes and additional 31 calendar days, in connection with the construction contract No. C-HCDD1-17-023-05-30 - Hidalgo County Drainage District No. 1 "Street and Drainage Improvements for Plena Vista Subdivision, Unit 2" as recommended by project engineer, Cruz-Hogan Consultants, Inc., and approved by HCDD1 General Manager, Mr. Raul E. Sesin, P.E., C.F.M., subject to compliance with HB1295.