CAPTION

1. Consideration and approval of a construction contract change order for the General Land Office (GLO) Contract No. 12-406-000-6453 for the Delta Area Connector East Lateral Project Ph. I & III. The change order will increase the current construction contract with Saenz Brothers Construction, LLC in the amount of $133,864.88.
2. Consideration and approval to authorize the County Judge to sign any and all documents associated with change orders and/or amendments pertaining to GLO Contract No. 12-406-000-6453.

BACKGROUND

The increase in construction contract price is due to bulk hauling and excavation services. Funding for this change order increase is being committed by HCDD # 1.

Current Contract Amount:     $2,871,013.80
Change Order # 4:                $   133,864.88
Total Contract Amount:         $3,589,687.68

Fiscal Impact

Attachments

Form Review

Inbox Reviewed By Date
Budget and Management Veronica Ortiz 01/30/2018 02:44 PM
Final Approval Monica Salinas 02/02/2018 05:07 PM
Form Started By:
olerma
Started On:
01/30/2018 08:38 AM
Final Approval Date:
02/02/2018