1. Consideration and approval of construction contract change order for the General Land Office (GLO) Contract No. 12-406-000-6453 for the Peñitas Drain Phase II project. Change Order No. 1 will increase the current construction contract with Mor-Wil, LLC in the amount of $318,973.50, and extend the time by an additional 60 calendar days.
2. Consideration and approval to authorize the County Judge to sign any and all documents associated with change orders and/or amendments pertaining to GLO Contract No. 12-406-000-6453.

BACKGROUND

The increase in construction contract price is due to excavation and embankment services required for construction of the drainage ditch. Funding for this change order increase is being committed by HCDD#1.

Current Contract Amount:     $1,796,206.39
Change Order # 4:                  $   318,973.50
Total Contract Amount:         $2,115,179.89

Fiscal Impact

Attachments

Form Review

Inbox Reviewed By Date
Budget and Management Veronica Ortiz 02/15/2018 11:33 AM
Final Approval Monica Salinas 02/16/2018 05:11 PM
Form Started By:
olerma
Started On:
02/14/2018 03:46 PM
Final Approval Date: