Skip to main content

AgendaQuick™

View Agenda Item

AI - 64234
3.
DRAINAGE - CONSENT
Meeting Date:
03/27/2018
Submitted For:
Jaime Salazar
Submitted By:
Moises Salazar, DRAINAGE DISTRICT
Department:
DRAINAGE DISTRICT

Information

CAPTION

Ratification of the fully executed Change Order No. 1, reflecting an increase of $2,513.00 in connection with the Drainage District No. 1 Office Site Fencing Project at 902 N. Doolittle Rd, Edinburg, TX, awarded to Central Fence & Supply, LTD (PO# 633649) as recommended by project engineer, Noe Saldivar, P.E., and approved by HCDD1 General Manager,  Mr. Raul E. Sesin, P.E., C.F.M.

BACKGROUND


Fiscal Impact

Attachments

Form Review

Inbox Reviewed By Date
Final Approval Monica Salinas 03/23/2018 04:53 PM
Form Started By:
moysalazar
Started On:
03/22/2018 04:02 PM
Final Approval Date:
03/23/2018