CAPTION

Ratification of the fully executed Change Order No. 4 in connection with contract No. C-16-378-02-21 with Clore Construction, LLC for the Hidalgo County Precinct #2 -Regional Linear Park Project (from Ridge Road to San Antonio Ave) as recommended by project engineer, Christopher Rodriguez, P.E. and subject to compliance with HB1295 when and if applicable.

BACKGROUND

Request for contract increase in the amount of $14,551.68 for an additional cost increase (material only) on additional quantities for Item H&B Illumination Assemblies.

Fiscal Impact

CALENDAR YEAR:
2018
ACCT. #:
8-1315-452-00-122-110-0-740
FUNDS AVAILABLE Y/N?:
Y/Pending
MATCHING FUNDS Y/N?:
N

BUDGETARY IMPACT:

Funding pending approval of AI#67493 CC 11/6/18.

Attachments

Form Review

Inbox Reviewed By Date
Purchasing / Internal msalazar 11/02/2018 11:24 AM
Budget and Management Veronica Ortiz 11/02/2018 02:02 PM
Final Approval Monica Salinas 11/02/2018 05:17 PM
Form Started By:
Erika Zamora
Started On:
11/01/2018 05:44 PM
Final Approval Date:
11/02/2018