AI- 68265
Purchasing Department 20.C.1.
CC - REGULAR
Prct. 4
- Meeting Date:
- 01/09/2019
- Submitted For:
- Nick Perez
- Submitted By:
- Nick Perez, COMM. PCT. #4
- Department:
- COMM. PCT. #4
Information
CAPTION
TXDOT PCT 4 (1315):
Acceptance and approval of Change Order No. 4 for (additional work items) with details as identified in CO#4 (attached herein) in connection to agreement # C-17-218-01-16 with Texas Cordia Construction, LLC. for "10th Street Extension Project" including authority for County Judge to sign the required document(s).
Acceptance and approval of Change Order No. 4 for (additional work items) with details as identified in CO#4 (attached herein) in connection to agreement # C-17-218-01-16 with Texas Cordia Construction, LLC. for "10th Street Extension Project" including authority for County Judge to sign the required document(s).
BACKGROUND
Change Order #4
Contract # C-17-218-01-16
CSJ: 0921-02-300
Project engineer - L&G
Contract # C-17-218-01-16
CSJ: 0921-02-300
Project engineer - L&G
Fiscal Impact
- CALENDAR YEAR:
- 2018
- ACCT. #:
- FUNDS AVAILABLE Y/N?:
- Y
- MATCHING FUNDS Y/N?:
BUDGETARY IMPACT:
Funds available as of 12/21/2018
TXDOT Participation 96.6% - $20,576.05
Local Participation 3.4% - $724.21
Account:
8-1315-431-00-124-030-0-XXX
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | msalazar | 12/27/2018 09:48 AM |
| Budget and Management | Veronica Ortiz | 12/27/2018 10:04 AM |
| Final Approval | Monica Salinas | 01/04/2019 06:26 PM |
- Form Started By:
- Nick Perez
- Started On:
- 12/21/2018 01:44 PM
- Final Approval Date:
- 01/04/2019