Skip to main content

AgendaQuick™

View Agenda Item

AI- 69518
Purchasing Department   21.C.1.
CC - REGULAR
Prct. 4
Meeting Date:
03/26/2019
Submitted For:
Marty Salazar
Submitted By:
Heidi Ortiz, PURCHASING DEPT.
Department:
PURCHASING DEPT.

Information

CAPTION

Requesting approval of Supplemental Agreement No. 2 to Agreement for Professional Services with L & G Consulting Engineers, Inc. d/b/a L & G Engineering (C-15-110-03-31) for the purpose of amending the contract to extend the termination date from March 29, 2019, to March 29, 2023, for the "FM 1925 (from 1,500 ft. West of 10th Street to McColl Rd) project to complete the scope of services as outlined in Exhibit "C" - Work Schedule.

BACKGROUND


Fiscal Impact

CALENDAR YEAR:
2019
ACCT. #:
9-1315-431-00-124-154-0-841
FUNDS AVAILABLE Y/N?:
Y
MATCHING FUNDS Y/N?:

BUDGETARY IMPACT:

PO No. 725312

CALENDAR YEAR:
2019
ACCT. #:
9-1315-431-00-124-154-0-721
FUNDS AVAILABLE Y/N?:
Y
MATCHING FUNDS Y/N?:

BUDGETARY IMPACT:

Attachments

Form Review

Inbox Reviewed By Date
Purchasing / Internal msalazar 03/22/2019 02:52 PM
Budget and Management Veronica Ortiz 03/22/2019 02:58 PM
Final Approval Monica Salinas 03/22/2019 05:59 PM
Form Started By:
hortiz
Started On:
03/21/2019 02:11 PM
Final Approval Date:
03/22/2019