CAPTION
Acceptance and approval to execute final AIA Document A133-2009 Guaranteed Maximum Price Amendment No. 1 between Hidalgo County and contractor, Erickson Construction, LLC. for the "Construction of Tax Office Substation" in the Precinct No. 1 Area, for the amount of $1,199,600.00 including authority to issue a Notice to Proceed [NTP].
BACKGROUND
Contract No. C-18-181-07-31
Fiscal Impact
- CALENDAR YEAR:
- 2019
- ACCT. #:
- 9-1353-419-40-121-253-0-730
- FUNDS AVAILABLE Y/N?:
- MATCHING FUNDS Y/N?:
BUDGETARY IMPACT:
PO 795783Available Amount on Account: $831,285.50
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | msalazar | 08/02/2019 04:39 PM |
| Budget and Management | Veronica Ortiz | 08/02/2019 04:40 PM |
| Final Approval | Monica Salinas | 08/02/2019 05:15 PM |
- Form Started By:
- yislas
- Started On:
- 07/19/2019 01:47 PM
- Final Approval Date:
- 08/02/2019