AI- 71598
Purchasing Department 7.A.
CC CONSENT SPECIAL
Prct. 4
- Meeting Date:
- 08/06/2019
- Submitted For:
- Nick Perez
- Submitted By:
- Nick Perez, COMM. PCT. #4
- Department:
- COMM. PCT. #4
Information
CAPTION
Approval of the following invoices (for processing and payment) as submitted by contracted project engineer, contractor, and architect; L&G Consulting Engineers, Inc., Texas Cordia Construction LLC., B2Z Engineering, & Mata-Garcia Architects, LLP:
| Invoice No. | Invoice Date | Project | Invoice Amount | P.O. Number |
| 40069 | 08/1/2019 | Memorial Park Construction Phase Services | $ 1,306.71 | 767241 |
| 11327694 | 07/31/2019 | FM1925 WA#1 1,500 ft. W. of FM2220 to 10th | $ 14,722.51 | 739761 |
| 11327693 | 07/31/2019 | FM1925 (10th Street to McColl) | $ 3,905.75 | 725312 |
| 11327673 | 07/31/2019 | 10th Street Extension Project WA#2 | $ 18,306.57 | 700265 |
| 11327685 | 07/31/2019 | Mile 5 Project WA#1 | $ 1,800.00 | 740893 |
| 11327695 | 07/31/2019 | FM2220 (Ware Road) Project WA#1 | $ 39,161.69 | 728311 |
| 11327692 | 07/31/2019 | FM1925 (Phase II) WA#1 | $ 2,856.16 | 703928 |
| 11327679 | 07/31/2019 | Cesar Chavez Re-Alignment WA#1 | $ 1,495.00 | 783997 |
| 18 | 08/01/2019 | 10th St Extension Project | $ 13,617.16 | 774917 |
| 3395-19 | 03/08/2019 | Linn-San Manuel Emergency Srv. Building (Reimbursable Expenses) | $ 2,211.50 | 802223 |
| 3394-19 | 03/08/2019 | San Carlos Community Resource Center (Reimbursable Expenses) | $ 2,211.50 | 802222 |
BACKGROUND
Fiscal Impact
- CALENDAR YEAR:
- 2019
- ACCT. #:
- Various
- FUNDS AVAILABLE Y/N?:
- Y
- MATCHING FUNDS Y/N?:
- N
BUDGETARY IMPACT:
Fiscal impact addressed by display of PO on agenda caption. funds available as of 8/2/19Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | msalazar | 08/02/2019 04:41 PM |
| Budget and Management | Veronica Ortiz | 08/02/2019 04:42 PM |
| Merlen P. Munoz | mmunoz | 08/02/2019 05:03 PM |
| Final Approval | Monica Salinas | 08/02/2019 05:14 PM |
- Form Started By:
- Nick Perez
- Started On:
- 08/02/2019 04:15 PM
- Final Approval Date:
- 08/02/2019