CAPTION
Requesting approval of Change Order No. 2 (C-18-199-02-12) with Texas Cordia Construction, LLC for the Hidalgo County Precinct #2 -Regional Linear Park Project - Section 2 (from Ridge Road to Hall Acres Road) as recommended by project engineer, Saul Muñoz, P.E..
BACKGROUND
Request for contract increase in the amount of $75,766.60 due to additional work to re-establish drainage on Cage Blvd. (US 281) after installing a 12X18 pedestrian tunnel for this project.
Fiscal Impact
- CALENDAR YEAR:
- 2019
- ACCT. #:
- 9-1315-452-00-122-110-8-740
- FUNDS AVAILABLE Y/N?:
- Y/Pending
- MATCHING FUNDS Y/N?:
- N
BUDGETARY IMPACT:
Funding available in the amount of $3,161.32 as of 8/9/19 and AI#71740 will be approved by CC 8/13/19 in the amount of $75,766.60.Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | msalazar | 08/09/2019 04:53 PM |
| Final Approval | Monica Salinas | 08/09/2019 06:02 PM |
- Form Started By:
- Erika Zamora
- Started On:
- 08/09/2019 04:21 PM
- Final Approval Date:
- 08/09/2019