Skip to main content

AgendaQuick™

View Agenda Item

AI- 73336
Planning Department   14.C.
CC REGULAR AGENDA REGULAR MTG
Meeting Date:
11/26/2019
Submitted For:
Flor Castillo
Submitted By:
Flor Castillo, PLANNING DEPT.
Department:
PLANNING DEPT.

CAPTION

1. Preliminary Approval
a. America Business Industrial Park Subdivision- Pct. 2 (Terry McGovern) (Alamo Road & Juan Balli Road)
 No. of Lots: 46 Industrial
 Estimated number of streetlights: 11
 Flood Zone: C & A
 Drainage: Yes, Drainage will be provided by storm sewer system and detention will be provided by widening the existing drain ditch.
 ETJ: No, Rural Area
 Water: Yes, provided by Military Highway Water Supply Corporation.
 Sewer: Yes, OSSF’s
Paved: Yes, Alamo Road is paved and 2 internal streets to be paved.
 
2. Final Approval
a. Alyssa Marie Torres Subdivision- Pct. 3 (Eberardo Torres) (Doffing Road & Mile 7 North Road)
 No. of Lots: 1 Single Family
 Flood Zone: X
 Drainage: Yes, Drainage will be provided by natural perculation within the proposed lots and surface runoff will drain into Doffing Road (F.M. 492) side ditch.
 ETJ: Yes, approved by the City of McAllen.
 Water: Yes, provided by Agua SUD.
 Sewer: Yes, OSSF has been installed.
 Paved: Yes, Doffing Road is paved.
 
b. Josie Vera Subdivision- Pct. 4 (Mark A. Vera & Jessica Rios) (Cesar Chavez Road & Richardson Road)
 No. of Lots: 5 Single Family
 Flood Zone: X
 Drainage:  Yes, Drainage will be provided by natural perculation within the proposed lots and surface runoff will drain into
Cesar Chavez Road side ditch.
 ETJ: Yes, approved by the City of Edinburg.
 Water: Yes, provided by North Alamo Water Supply Corporation.
 Sewer: Yes, OSSF’s have been installed.
 Paved: Yes, Cesar Chavez Road is paved.
 
c. La Reserva Phase 1-B Subdivision- Pct. 4 (William A. Schwarz) (Mile 20 North Road & Uresti Road)
 No. of Lots: 27 Single Family
 Streetlights: 6
 Flood Zone: X & A
 Drainage: Yes, Drainage has been provided by storm sewer system and detention has been provided on the existing drain ditch.
 ETJ: Yes, approved by the City of Edinburg.
 Water: Yes, provided by North Alamo Water Supply Corporation.
 Sewer: Yes, OSSF’s have been installed.
 Paved: Yes, Mile 20 North Road, Uresti Road and 1 internal street are paved.
 
d. Camino De Abram Subdivision Phase II - Pct. 3 (Everman Dev., LLC) (Abram Road & Mile 3 North Road)
 No. of Lots: 99 Single Family
 Streetlights: 15
 Flood Zone: C
 Drainage: Yes, Drainage will be provided by storm sewer system discharging to an existing Regional Drainage Detention Facility.
 ETJ: Yes, approved by the City of Mission.
 Water: Yes, provided by Agua SUD.
 Sewer: Yes, OSSF’s have been installed.
 Paved: Yes, Abram Road and 3 internal streets are paved.
 
e. Las Encinitas Phase I Subdivision- Pct. 4 (Forrest N. Runnels, Jr.) (Monte Cristo Road & Brushline Road)
 No. of Lots: 114 Single Family, 10 Commercial
 Streetlights: 47
 Flood Zone: X
 Drainage: Yes, Drainage will be provided by storm sewer system and detention will be provided by widening the existing drain ditch.
 ETJ: Yes, approved by the City of Edinburg.
 Water: Yes, provided by North Alamo Water Supply Corporation.
 Sewer: Yes, OSSF’s for residential lots have been installed.
 Paved: Yes, Monte Cristo Road and 6 internal streets are paved.
 
3. Final Approval with Financial Guarantee
a. Las Comadres #5 Subdivision - Pct. 3 (Carlos G. Leal, Jr.) (Texan Avenue & Mile 4 North Road)
 No. of Lots: 76 Single Family
 Streetlights: 20
 Flood Zone: X
 Drainage: Yes, Drainage consists of storm sewer system discharging to HCDD#1 Regional Detention Facility approximately ½ mile southwest from the proposed subdivision.
 ETJ: Yes, approved by the City of Mission.
 Water: Yes, provided by Agua SUD.
 Sewer: Yes, OSSF’s have been installed.
 *Final Approval with Cash Deposit in the amount of 15,328.00 for 2 Shared Driveways and 2 Single Driveways.
 Paved: Yes, Texan Avenue and 4 internal streets are paved.
 

BACKGROUND


Fiscal Impact

Attachments

Form Review

Inbox Reviewed By Date
Budget and Management Veronica Ortiz 11/20/2019 02:32 PM
Final Approval Monica Salinas 11/22/2019 05:19 PM
Form Started By:
Flor Castillo
Started On:
11/20/2019 01:54 PM
Final Approval Date:
11/22/2019