AI- 75112
Purchasing Department 14.I.
CC CONSENT AGENDA SPECIAL MTG
Prct. 2
- Meeting Date:
- 04/07/2020
- Submitted For:
- Eddie Cantu
- Submitted By:
- Erika Zamora, COMM. PCT. #2
- Department:
- COMM. PCT. #2
Information
CAPTION
Requesting approval of Change Order No 4 and 5 (C-19-017-11-15) with 2GS, LLC dba Earthworks Enterprise for the Hidalgo County Precinct #2 - Dicker Road Reconstruction Project from (23rd Street to Jackson Road) as recommended by the project engineer, Saul Muñoz, P.E.
BACKGROUND
CO #4-To change current backfill requirements to expedite construction and reduce construction cost;
CO #5-Modify traffic control plan between Jackson Rd and McColl Rd
Change Orders 4 and 5 will decrease the contract $511,387.78.
CO #5-Modify traffic control plan between Jackson Rd and McColl Rd
Change Orders 4 and 5 will decrease the contract $511,387.78.
Fiscal Impact
- CALENDAR YEAR:
- 2020
- ACCT. #:
- 0-1315-431-00-122-062-0-721
- FUNDS AVAILABLE Y/N?:
- Y
- MATCHING FUNDS Y/N?:
- N
BUDGETARY IMPACT:
Change Order No. 4 & 5 reduce the construction contract amount so a PO cancellation will be submitted to Purchasing.Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | msalazar | 04/03/2020 02:32 PM |
| Budget and Management | Veronica Ortiz | 04/03/2020 02:39 PM |
| Final Approval | Monica Salinas | 04/03/2020 05:27 PM |
- Form Started By:
- Erika Zamora
- Started On:
- 04/03/2020 12:02 PM
- Final Approval Date:
- 04/03/2020