Information
CAPTION
Requesting approval of Change Order No. 6 reflecting an increase in the amount of $90,795.12, and thirty (30) additional construction calendar days, in connection with Contract No. C-HCDD1-19-002-01-09 -Hidalgo County Drainage District No. 1 project, "Pharr-McAllen Drain Improvements -2018 Bond Referendum Project #31" with Mor-Wil, LLC, as recommended by Project Engineer David Saenz, PE, L & G Engineering.
BACKGROUND
Compliance with HB1295 has been met.