AI- 7647
14.K.1.
CC REGULAR
Meeting Date:
01/30/2008
Submitted For:
Rocio Villarreal
Submitted By:
Rocio Villarreal, PURCHASING DEPT.
Department:
PURCHASING DEPT.

CAPTION

Requesting approval for the B141- AIA Agreement for Professional Architect Services between Hidalgo County and Gignac & Associates, (as approved for negotiation on CC 05-15-07) in connection with the design and construction of "Sheriff's Office Substation in the areas of Precinct No. 1 and No. 3" and subject to legal review. 

BACKGROUND


Fiscal Impact

FISCAL YEAR:
2007
ACCT. #:
7-1336-423-00-280-036-0-720
FUNDS AVAILABLE Y/N?:
Y
MATCHING FUNDS Y/N?:
N

BUDGETARY IMPACT:

Precinct# 1 Substation Available Balance as of 1-25-08 $3,000,000.00; Precinct#3 Substation to be determined in a later date. 

Attachments

Form Review

Inbox Reviewed By Date
Purchasing / Internal msalazar 01/24/2008 03:43 PM
Budget and Management Dina Trevino 01/24/2008 03:44 PM
Auditor's Office 01/25/2008 05:49 PM
Form Started By:
Rocio Villarreal
Started On:
01/23/2008 04:06 PM
Final Approval Date: