AI - 77143
3.B.
DD-CONSENT AGENDA SPECIAL MTG
- Meeting Date:
- 09/01/2020
- Submitted For:
- Jaime Salazar
- Submitted By:
- Moises Salazar, DRAINAGE DISTRICT
- Department:
- DRAINAGE DISTRICT
Information
CAPTION
Ratification of the fully executed Change Order No. 1 reflecting ninety-two (92) additional construction calendar days, in connection with contract No. C-HCDD1-19-074-11-26 -Hidalgo County Drainage District No. 1 "Mission Lateral (Section I) -2018 Bond Referendum project #26" with Saenz Brothers Construction as recommended by project engineer, Damien B. Tijerina, P.E., L&G Engineering, and approved by HCDD1 General Manager, Mr. Raul E. Sesin, P.E., CFM. (subject to compliance to HB1295).
BACKGROUND
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Nora Cavazos | 08/28/2020 05:43 PM |
- Form Started By:
- moysalazar
- Started On:
- 08/28/2020 01:25 PM
- Final Approval Date:
- 08/28/2020