AI- 78370
Purchasing Department 8.E.
CC CONSENT AGENDA REGULAR MTG
Facilities Management
- Meeting Date:
- 11/24/2020
- Submitted For:
- Daniel Flores
- Submitted By:
- JC Carreon, FACILITIES MANAGEMENT
- Department:
- FACILITIES MANAGEMENT
CAPTION
New Courthouse Bus Shelter Project:
Requesting approval and authorization of payment to Noble Texas Builders for Application #1 in the amount of $12,905.00 with authority for County Treasurer to issue payment after review and auditing procedures are completed by County Auditor (bus shelter project).
BACKGROUND
Bid awarded by CC 06-23-20 AI #76089
CC - 8/11/20 AI # 76800 - Construction contract with Noble Texas Builders, LLC, C-19-280-08-11, for "ADA Bus Shelter on N. 12th Ave and Stubbs St."
Fiscal Impact
- CALENDAR YEAR:
- 2020
- ACCT. #:
- 0-1100-419-40-125-035-0-430
- FUNDS AVAILABLE Y/N?:
- y-pending
- MATCHING FUNDS Y/N?:
BUDGETARY IMPACT:
Funds available through PO# 824280 (PO mod. will be requested from obj. 730 to 430 as per auditor's request)Transfer of funds CC 11/24/20 AI #78424
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | msalazar | 11/19/2020 06:07 PM |
| Budget and Management | Veronica Ortiz | 11/20/2020 08:07 AM |
| Final Approval | Monica Salinas | 11/20/2020 06:27 PM |
- Form Started By:
- jccarreon
- Started On:
- 11/19/2020 02:35 PM
- Final Approval Date:
- 11/20/2020