CAPTION
PD Lateral - Budget 529
Approval to issue payment on Application for Payment No. 3 in the amount of $158,909.95 from Mor-Wil, LLC pertaining to Construction Contract No. C-HCDD1-20-029-06-23. Project Engineer: Izaguirre Engineering, PO#640212
Approval to issue payment on Application for Payment No. 3 in the amount of $158,909.95 from Mor-Wil, LLC pertaining to Construction Contract No. C-HCDD1-20-029-06-23. Project Engineer: Izaguirre Engineering, PO#640212