AI - 81501
6.A.
DD-REGULAR AGENDA SPECIAL MTG
- Meeting Date:
- 07/13/2021
- Submitted For:
- Jaime Salazar
- Submitted By:
- Moises Salazar, DRAINAGE DISTRICT
- Department:
- DRAINAGE DISTRICT
Information
CAPTION
Requesting approval of Change Order No. 1 reflecting an increase in the amount of $75,685.52, and one hundred ninety (190) additional construction calendar days, in connection with contract No. C-HCDD1-20-034-08-11 -Hidalgo County Drainage District No. 1 "Jackson Rd. Drain Phase I -2018 Bond Referendum project #16" with RG Enterprises, LLC dba G&G Contractors, as recommended by project engineer, Quintanilla, Headley & Associates, Inc., (subject to compliance to HB1295).
BACKGROUND
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Nora Cavazos | 07/09/2021 04:57 PM |
- Form Started By:
- moysalazar
- Started On:
- 07/02/2021 01:13 PM
- Final Approval Date:
- 07/09/2021