AI - 81519
4.A.
DD-CONSENT AGENDA SPECIAL MTG
- Meeting Date:
- 07/13/2021
- Submitted For:
- Jaime Salazar
- Submitted By:
- Rocio Villarreal, DRAINAGE DISTRICT
- Department:
- DRAINAGE DISTRICT
Information
CAPTION
Requesting approval of Change Order No. 3 reflecting an additional Forty-Five (45) construction calendar days, in connection with the contract C-HCDD1-20-038-09-08-"Delta Regional Water Management Project Phase I (Panchitas Detention Pond) -2013 Bond Series" with Saenz Brothers Construction, and as recommended by Project Engineer, Jose Noe Saldivar, P.E., HCDD1 Engineer IV.
BACKGROUND
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Nora Cavazos | 07/09/2021 05:33 PM |
- Form Started By:
- Rocio Villarreal
- Started On:
- 07/06/2021 11:24 AM
- Final Approval Date:
- 07/09/2021