Ratification of the fully executed Change Order No. 1 reflecting an increase in the amount of $32,061.22, and additional Ninety (90)  construction calendar days, in connection with the Contract C-HCDD1-20-039-08-25 -"Mile 9 N & FM 1015 - Package 1A Improvements - 2018 Bond Referendum Project #24" with Mor-Wil, LLC as recommended by Project Engineer, Robert Saenz, PE, Halff Associates, Inc, and approved by HCDD1 General Manager, Raul E. Sesin, P.E., CFM.

BACKGROUND


Fiscal Impact

Attachments

Form Review

Inbox Reviewed By Date
Final Approval Nora Cavazos 07/09/2021 05:33 PM
Form Started By:
Nora Cavazos
Started On:
07/09/2021 05:22 PM
Final Approval Date:
07/09/2021