CAPTION
Requesting approval of Change Order No.1 in connection with Contract No. C-18-181A-03-26 and GMP Amendment No.1 with E-Con Group, LLC for the Sunset Park Operations Facility Project in Pct.1 as recommended by project engineer B2Z Engineering, LLC.
BACKGROUND
AI-69442 - Authority/Approval for the Precinct Commissioner or designee: David Suarez, to execute change orders that involve.. "an increase or decrease in the cost of $50,000 or less and in no event to exceed the change order statutory limits"
The contract time will be increased by Forty-Four (44) calendar days due to inclement weather and for days associated with Change Proposal Request No.11 for the changes in the compressed air lines.
(27) days for inclement weather
(17) days associated with CPR No.11 - Compressed Air Lines
The new date of Substantial Completion will be September 02, 2021.
The contract time will be increased by Forty-Four (44) calendar days due to inclement weather and for days associated with Change Proposal Request No.11 for the changes in the compressed air lines.
(27) days for inclement weather
(17) days associated with CPR No.11 - Compressed Air Lines
The new date of Substantial Completion will be September 02, 2021.
Fiscal Impact
- CALENDAR YEAR:
- 2021
- ACCT. #:
- 1-1357-431-00-121-237-0-730
- FUNDS AVAILABLE Y/N?:
- Y
- MATCHING FUNDS Y/N?:
BUDGETARY IMPACT:
Changes will have no fiscal impact.Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | msalazar | 07/23/2021 04:31 PM |
| Budget and Management | ngonzalez1 | 07/23/2021 04:33 PM |
| Final Approval | Monica Salinas | 07/24/2021 09:44 AM |
- Form Started By:
- Hector Garcia
- Started On:
- 07/21/2021 05:58 PM
- Final Approval Date:
- 07/24/2021