Ratification of the fully executed Change Order No. 1 reflecting One Hundred and Twenty (120) additional calendar days, in connection with Contract C-HCDD1-20-063-11-12, “P.S.J.A. Lateral Drain Ditch Improvements (Earling Road to South Main Drain Phase I)" with  Saenz Brothers Construction, LLC, and as recommended by Project Engineer, Javier Hinojosa Engineering, and approved by HCDD1 General Manager, Raul E. Sesin, P.E., CFM. 