CAPTION
Ratification of the fully executed Change Order No. 1 reflecting an increase in the amount of $1,075.52, and fifteen (15) additional construction calendar days, in connection with Contract No. C-HCDD1-21-024-06-16 -"J-08 Drain-McColl Rd. Culvert Crossing-2018 Bond Referendum Project#15" with RDH Site and Concrete, LLC, as recommended by project engineer, Jose Noe Saldivar, P.E., HCDD1 Engineer IV (subject to compliance to HB1295).