AI - 82976
5.B.
DD-CONSENT AGENDA SPECIAL MTG
Meeting Date:
10/19/2021
Submitted For:
Jaime Salazar
Submitted By:
Rocio Villarreal, DRAINAGE DISTRICT
Department:
DRAINAGE DISTRICT

Information

CAPTION

Ratification of the fully executed Change Order No. 1  reflecting an increase in the amount of $1,075.52, and fifteen (15) additional construction calendar days, in connection with Contract No. C-HCDD1-21-024-06-16 -"J-08 Drain-McColl Rd. Culvert Crossing-2018 Bond Referendum Project#15" with RDH Site and Concrete, LLC, as recommended by project engineer, Jose Noe Saldivar, P.E., HCDD1 Engineer IV (subject to compliance to HB1295).