1. Preliminary Approval with Variance Request
a. A.J. Vasquez Subdivision- Pct. 1 (Juan B. Vasquez) (Mile 16 North Road & Mile 6 West Road)
No. of Lots: 1 Single Family
Flood Zone: X
Estimated Number of Streetlights:N/A
Filling Stations:N/A
Drainage: Yes, Drainage will be provided by natural perculation and surface runoff onto Mile 16 North Road side ditch.
ETJ: Yes, City of Elsa however the city has decided to opt out from the review process and/or approve the subdivision.
Water: Yes, provided by North Alamo Water Supply Corporation.
Sewer: Yes, OSSF.
Paved: Yes, Mile 16 North Road is paved.
b. Vargas Subdivision- Pct. 3 (Cristo Salvador Vargas) (Mile 5 Road & Minnesota Road)
No. of Lots: 1 Single Family
Flood Zone: X
Estimated Number of Streetlights:N/A
Filling Stations:N/A
Drainage: Yes, Drainage will be provided by natural perculation and surface runoff onto Mile 5 North Road side ditch.
ETJ: Yes, approved by the City of Mission.
Water: Yes, provided by Agua SUD.
Sewer: Yes, OSSF.
Paved: Yes, Mile 5 Road is paved.
c. Monarco Estates Subdivision- Pct. 4 (Cayetano Development, LLC.) (Owassa Road & Alamo Road)
No. of Lots: 167 Single Family
Flood Zone: B
Estimated Number of Streetlights:23
Filling Stations:9
Drainage: Yes, Drainage will be provided by storm sewer system and detention will be provided by widening the existing drain ditch.
ETJ: Yes, Approved by the City of Edinburg.
Water: Yes, provided by North Alamo Water Supply Corporation.
Sewer: Yes, provided by North Alamo Water Supply Corporation.
Paved: Yes, Owassa Road is paved and 7 internal streets to be paved.
2. Preliminary Approval
a. Tres Maravillas Subdivision- Pct. 1 (Tres Maravillas, LLC.) (Mile 9 ½ North Road & Victoria Road)
No. of Lots: 49 Single Family
Flood Zone: X
Estimated Number of Streetlights:11
Filling Stations:6
Drainage: Yes, Drainage will be provided by storm sewer system and detention will be provided by widening the existing drain ditch.
ETJ: Yes, approved by the City of Donna.
Water: Yes, provided by North Alamo Water Supply Corporation.
Sewer: Yes, OSSF’S.
Paved: Yes, Mile 9 ½ North Road is paved and 3 internal streets to be paved.
b. El Encantado Subdivision- Pct. 1 (E&W COHRS, LLC.) (Mile 9 North Road & Hutto Road)
No. of Lots: 322 Single Family
Flood Zone: C
Estimated Number of Streetlights:49
Filling Stations:22
Drainage: Yes, Drainage will be provided by storm sewer system and detention will be provided by widening the existing drain ditch.
ETJ: Yes, approved by the City of Donna.
Water: Yes, provided by North Alamo Water Supply Corporation.
Sewer: Yes, provided by North Alamo Water Supply Corporation.
Paved: Yes, Mile 9 North Road and Hutto Road are paved.11 internal streets to be paved.
c. San Pedro Estates Subdivision- Pct. 1 (Humberto Garcia) (Mile 6 ½ West Road & Mile 6 ½ North Road)
No. of Lots: 16 Single Family
Flood Zone: X
Estimated Number of Streetlights:N/A
Filling Stations:4
Drainage: Yes, Drainage will be provided by natural perculation and surface runoff onto Mile 6 ½ West Road side ditch.
ETJ: Yes, approved by the City of Weslaco.
Water: Yes, provided by North Alamo Water Supply Corporation.
Sewer: Yes, OSSF’S.
Paved: Yes, Mile 6 ½ West Road and Mile 6 ½ North Road are paved.
3. Final Approval with Financial Guarantee
a. Riojas-Camacho Subdivision- Pct. 1 (Pedro & Delia Riojas) (Mesquite Circle & Mile 14 ½ North Road)
No. of Lots: 2 Single Family
Flood Zone: X
Number of Streetlights:N/A
Filling Stations:N/A
Drainage: Yes, The proposed drainage for this subdivision will be utilizing the existing detention pond within Resaca Escondida Subdivision.
ETJ: No, Rural Area.
Water: Yes, provided by North Alamo Water Supply Corporation.
Sewer: Yes, (1) OSSF has been escrowed for Lot 1 and Lot 2 has an existing OSSF.
Paved: Yes, Mesquite Circle is paved.
* Final Approval with a cash deposit in the amount of $1,500.00 for (1) OSSF.
4. Final Approval
a. AEP Progreso Substation Subdivision- Pct. 1 (American Power Electric [AEP]) (U.S. Hwy 281 & F.M. 88)
No. of Lots: 1 Industrial
Flood Zone: C
Number of Streetlights:N/A
Filling Stations:N/A
Drainage: Yes, Drainage will be provided by onsite detention at building permit stage.
ETJ: Yes, approved by the City of Weslaco.
Water: Yes, provided by Military Highway Water Supply Corporation.
Sewer: Yes, OSSF will be installed at building permit stage.
Paved: Yes, U.S. Hwy 281 is paved.
b. T & O Ranch No. 2 Subdivision - Pct. 4 (T&O Ranch Investments) (Benito Ramirez Road & Brushline Road)
No. of Lots: 4 Single Family
Flood Zone: X
Number of Streetlights:N/A
Filling Stations:1
Drainage: Yes, Drainage will be provided by natural perculation and surface runoff onto Benito Ramirez Road side ditch.
ETJ: Yes, City of Edinburg.
Water: Yes, provided by North Alamo Water Supply Corporation.
Sewer: Yes, OSSF’S have been installed
Paved: Yes, Benito Ramirez Road is paved.
c. Western Oaks Subdivision - Pct. 3 (Rigoberto Villarreal) (Western Road & Mile 6 North Road)
No. of Lots: 42 Single Family
Flood Zone: X
Number of Streetlights:18
Filling Stations:9
Drainage: Yes, Drainage will be provided by storm sewer system and detention will be provided by regional detention areas dedicated to HCDD#1.
ETJ: Yes, approved by the City of Mission.
Water: Yes, provided by Agua SUD.
Sewer: Yes, OSSF’S have been installed
Paved: Yes, Western Road, Abram Road and 3 internal streets are paved.
a. A.J. Vasquez Subdivision- Pct. 1 (Juan B. Vasquez) (Mile 16 North Road & Mile 6 West Road)
No. of Lots: 1 Single Family
Flood Zone: X
Estimated Number of Streetlights:N/A
Filling Stations:N/A
Drainage: Yes, Drainage will be provided by natural perculation and surface runoff onto Mile 16 North Road side ditch.
ETJ: Yes, City of Elsa however the city has decided to opt out from the review process and/or approve the subdivision.
Water: Yes, provided by North Alamo Water Supply Corporation.
Sewer: Yes, OSSF.
Paved: Yes, Mile 16 North Road is paved.
b. Vargas Subdivision- Pct. 3 (Cristo Salvador Vargas) (Mile 5 Road & Minnesota Road)
No. of Lots: 1 Single Family
Flood Zone: X
Estimated Number of Streetlights:N/A
Filling Stations:N/A
Drainage: Yes, Drainage will be provided by natural perculation and surface runoff onto Mile 5 North Road side ditch.
ETJ: Yes, approved by the City of Mission.
Water: Yes, provided by Agua SUD.
Sewer: Yes, OSSF.
Paved: Yes, Mile 5 Road is paved.
c. Monarco Estates Subdivision- Pct. 4 (Cayetano Development, LLC.) (Owassa Road & Alamo Road)
No. of Lots: 167 Single Family
Flood Zone: B
Estimated Number of Streetlights:23
Filling Stations:9
Drainage: Yes, Drainage will be provided by storm sewer system and detention will be provided by widening the existing drain ditch.
ETJ: Yes, Approved by the City of Edinburg.
Water: Yes, provided by North Alamo Water Supply Corporation.
Sewer: Yes, provided by North Alamo Water Supply Corporation.
Paved: Yes, Owassa Road is paved and 7 internal streets to be paved.
2. Preliminary Approval
a. Tres Maravillas Subdivision- Pct. 1 (Tres Maravillas, LLC.) (Mile 9 ½ North Road & Victoria Road)
No. of Lots: 49 Single Family
Flood Zone: X
Estimated Number of Streetlights:11
Filling Stations:6
Drainage: Yes, Drainage will be provided by storm sewer system and detention will be provided by widening the existing drain ditch.
ETJ: Yes, approved by the City of Donna.
Water: Yes, provided by North Alamo Water Supply Corporation.
Sewer: Yes, OSSF’S.
Paved: Yes, Mile 9 ½ North Road is paved and 3 internal streets to be paved.
b. El Encantado Subdivision- Pct. 1 (E&W COHRS, LLC.) (Mile 9 North Road & Hutto Road)
No. of Lots: 322 Single Family
Flood Zone: C
Estimated Number of Streetlights:49
Filling Stations:22
Drainage: Yes, Drainage will be provided by storm sewer system and detention will be provided by widening the existing drain ditch.
ETJ: Yes, approved by the City of Donna.
Water: Yes, provided by North Alamo Water Supply Corporation.
Sewer: Yes, provided by North Alamo Water Supply Corporation.
Paved: Yes, Mile 9 North Road and Hutto Road are paved.11 internal streets to be paved.
c. San Pedro Estates Subdivision- Pct. 1 (Humberto Garcia) (Mile 6 ½ West Road & Mile 6 ½ North Road)
No. of Lots: 16 Single Family
Flood Zone: X
Estimated Number of Streetlights:N/A
Filling Stations:4
Drainage: Yes, Drainage will be provided by natural perculation and surface runoff onto Mile 6 ½ West Road side ditch.
ETJ: Yes, approved by the City of Weslaco.
Water: Yes, provided by North Alamo Water Supply Corporation.
Sewer: Yes, OSSF’S.
Paved: Yes, Mile 6 ½ West Road and Mile 6 ½ North Road are paved.
3. Final Approval with Financial Guarantee
a. Riojas-Camacho Subdivision- Pct. 1 (Pedro & Delia Riojas) (Mesquite Circle & Mile 14 ½ North Road)
No. of Lots: 2 Single Family
Flood Zone: X
Number of Streetlights:N/A
Filling Stations:N/A
Drainage: Yes, The proposed drainage for this subdivision will be utilizing the existing detention pond within Resaca Escondida Subdivision.
ETJ: No, Rural Area.
Water: Yes, provided by North Alamo Water Supply Corporation.
Sewer: Yes, (1) OSSF has been escrowed for Lot 1 and Lot 2 has an existing OSSF.
Paved: Yes, Mesquite Circle is paved.
* Final Approval with a cash deposit in the amount of $1,500.00 for (1) OSSF.
4. Final Approval
a. AEP Progreso Substation Subdivision- Pct. 1 (American Power Electric [AEP]) (U.S. Hwy 281 & F.M. 88)
No. of Lots: 1 Industrial
Flood Zone: C
Number of Streetlights:N/A
Filling Stations:N/A
Drainage: Yes, Drainage will be provided by onsite detention at building permit stage.
ETJ: Yes, approved by the City of Weslaco.
Water: Yes, provided by Military Highway Water Supply Corporation.
Sewer: Yes, OSSF will be installed at building permit stage.
Paved: Yes, U.S. Hwy 281 is paved.
b. T & O Ranch No. 2 Subdivision - Pct. 4 (T&O Ranch Investments) (Benito Ramirez Road & Brushline Road)
No. of Lots: 4 Single Family
Flood Zone: X
Number of Streetlights:N/A
Filling Stations:1
Drainage: Yes, Drainage will be provided by natural perculation and surface runoff onto Benito Ramirez Road side ditch.
ETJ: Yes, City of Edinburg.
Water: Yes, provided by North Alamo Water Supply Corporation.
Sewer: Yes, OSSF’S have been installed
Paved: Yes, Benito Ramirez Road is paved.
c. Western Oaks Subdivision - Pct. 3 (Rigoberto Villarreal) (Western Road & Mile 6 North Road)
No. of Lots: 42 Single Family
Flood Zone: X
Number of Streetlights:18
Filling Stations:9
Drainage: Yes, Drainage will be provided by storm sewer system and detention will be provided by regional detention areas dedicated to HCDD#1.
ETJ: Yes, approved by the City of Mission.
Water: Yes, provided by Agua SUD.
Sewer: Yes, OSSF’S have been installed
Paved: Yes, Western Road, Abram Road and 3 internal streets are paved.
BACKGROUND
Fiscal Impact
Attachments
- 1-A.J. VASQUEZ.; P-
- 2-VARGAS.; P
- 3-MONARCO EST.; P
- 4-TRES MARAVILLAS; Preliminary
- 5-EL ENCANTADO; Preliminary
- 6-SAN PEDRO ESTATES; Preliminary-
- 7-Riojas-Camacho;F-
- 8-AEP PROGRESO SUBSTATION FINAL
- 9-T&O Ranch #2
- 10-WESTERN OAKS;F
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Budget and Management | Veronica Ortiz | 11/17/2021 04:04 PM |
| Final Approval | Monica Salinas | 11/26/2021 11:52 AM |
- Form Started By:
- Flor Castillo
- Started On:
- 11/17/2021 02:47 PM
- Final Approval Date:
- 11/26/2021