CAPTION

Requesting approval of Change Order No.4 [increase] for Texas Cordia Construction, LLC [C-19-274-04-07], as recommended by the project engineer, SAMES, in connection to HC Precinct No.1-Mile 6 W Road Project (Mile 9 to Mile 11). 

BACKGROUND

Proj.# 22-0042

Manhole to be backfilled to ensure structural integrity, support to the vertical load of the asphalt pavement, and the imposed traffic loadings. The increase of this change order is for an estimated total of $2,662.30. Due to the nature of the Force Account Method, the final cost is to be confirmed once the work is done. 

Fiscal Impact

CALENDAR YEAR:
2022
ACCT. #:
2-1315-431-00-121-039-1-721
FUNDS AVAILABLE Y/N?:
Y
MATCHING FUNDS Y/N?:

BUDGETARY IMPACT:

Attachments

Form Review

Inbox Reviewed By Date
Purchasing / Internal ebelmarez 02/04/2022 03:47 PM
Budget and Management Veronica Ortiz 02/04/2022 04:05 PM
Final Approval Monica Salinas 02/04/2022 06:47 PM
Form Started By:
Hector Garcia
Started On:
01/20/2022 06:02 PM
Final Approval Date:
02/04/2022