CAPTION

Mission Inlet - Budget 020
1. Requesting approval of Application for Payment No. 8 in the amount of $47,485.12 from Castle Enterprises as it pertains to Mission Inlet Construction Contract C-HCDD1-20-002-02-11. Project Engineer-L&G Engineering PO#639479

Weslaco Drain - Budget 335
2. Requesting approval of Application for Payment No. 3 in the amount of $100,077.53 from Castle Enterprises as it pertains to Weslaco Drain Construction Contract C-HCDD1-21-017-06-1.  Project Engineer-HCDD1 Omar Anzaldua Jr, PE.

FM 495 & Donna Lateral - Budget 370
3. Requesting acceptance and approval of Certificate of Substantial Completion and Certificate of Construction Completion from Venser Contractors, LLC pertaining to FM 495 & Donna Lateral Construction Contract C-HCDD1-18-049-09-25. 
4. Requesting approval of Application for Payment No. 5-Retainage plus interest for a total amount of $33,180.04 from Venser Contractors, LLC pertaining to FM 495 & Donna Lateral construction contract C-HCDD1-18-049-09-25. Project Engineer-HCDD1 Raul E. Sesin, PE, CFM

BACKGROUND


Fiscal Impact

Attachments

Form Review

Inbox Reviewed By Date
Final Approval Nora Cavazos 03/04/2022 04:27 PM
Form Started By:
Alvaro Chuc
Started On:
03/04/2022 08:30 AM
Final Approval Date:
03/04/2022