AI- 85422
Purchasing Department 25.E.1.
CC REGULAR AGENDA SPECIAL MTG
Prct. 3
- Meeting Date:
- 04/19/2022
- Submitted By:
- Norma Ceballos, COMM. PCT. #3
- Department:
- COMM. PCT. #3
CAPTION
Requesting approval of Change Order No. 3 [C-20-294-02-23] with REIM Construction, Inc. for Hidalgo County Precinct No. 3 - Mile 3 N. Road Project (Tom Gill Road to FM 492 [Goodwin Road]) as recommended by project engineer, B2Z Engineering and subject to receipt of TXDOT letter of concurrence.
BACKGROUND
Subject to TXDOT Concurrence Letter
Change Order No. 3 adds both work and time to the original contract for removing hard rock while installing reinforced concrete pipe (RCP) in lines "A", "B", "C". Encountering rock was an unexpected and considered a differing site condition that was not identified within the Mile 3 project plans.
Change Order No. 3 is an increase in the amount of $236,635.00 and 70 days extension, for compensation and time for rock removal due to the unforeseen field conditions not included in the Mile 3 project plans.
County's participation is 1.4%
Fiscal Impact
- CALENDAR YEAR:
- 2022
- ACCT. #:
- 2-1315-431-00-123-051-0-XXX
- FUNDS AVAILABLE Y/N?:
- Y
- MATCHING FUNDS Y/N?:
BUDGETARY IMPACT:
Funds available in object codes 721 & 841 pending 2021 rollover.Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | ebelmarez | 04/13/2022 06:12 PM |
| Budget and Management | Veronica Ortiz | 04/14/2022 10:21 AM |
| Final Approval | Monica Salinas | 04/15/2022 04:20 PM |
- Form Started By:
- nceballos
- Started On:
- 04/12/2022 10:56 AM
- Final Approval Date:
- 04/15/2022