CAPTION

Ratification of the fully executed Change Order No. 4, in connection with the project "Jackson Road Drain Improvements Phase I -2018 Bond Referendum Project No. 16", to Contract No. C-HCDD1-20-034-08-11 reflecting an increase of $28,976.64 and Ninety(90)additional construction calendar days, with RG Enterprises, LLC dba G&G Contractors as recommended by Quintanilla, Headley & Associates, and approved by HCDD1 General Manager, Raul E. Sesin, P.E.,CFM

BACKGROUND

1. Contract Time Extension (Additional days to add riprap)
2. Additional 77 CY of riprap for existing pipes along Jackson Drain Canal (Riprap not noted on plans)
3. Additional days for delay due to vendor not having RCP for Hall Acres 

Compliance with HB -1295

Fiscal Impact

Attachments