AI - 86348
3.A.
DD-CONSENT AGENDA REGULAR MTG
- Meeting Date:
- 06/28/2022
- Submitted For:
- Jaime Salazar
- Submitted By:
- Rocio Villarreal, DRAINAGE DISTRICT
- Department:
- DRAINAGE DISTRICT
CAPTION
Ratification of the approved and fully executed Change Order No. 1 with Saenz Brothers Construction (C-HCDD1-21-044-11-02) reflecting an additional forty (40) Construction Calendar Days, "San Carlos -83rd St-87th St Drainage Improvements Outfall" and as recommended by Assistant General Manager, Omar Anzaldua, Jr., PE, CFM, PMP, CCM, and as approved by HCDD1 General Manager, Raul E. Sesin, P.E., CFM.
BACKGROUND
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Nora Cavazos | 06/24/2022 04:08 PM |
- Form Started By:
- Rocio Villarreal
- Started On:
- 06/22/2022 03:27 PM
- Final Approval Date:
- 06/24/2022