Requesting ratification of approved and fully executed Notice to Resume Work Order issued to Gonzalez Engineering & Management, LLC for Construction Contract No. C-HCDD1-21-023-07-27, "Mission-McAllen Rado Alternate-Phase I -2018 bond Referendum Project No. 25" as recommended by Project Engineer: B2Z Engineering, and approved by HCDD1 Assistant General Manager, Omar Anzaldua, Jr., PE, CFM, PMP, CCM (Subject to compliance to HB1295). Resume Order effective date June 23, 2022.