AI - 86582
3.A.
DD-CONSENT AGENDA REGULAR MTG
- Meeting Date:
- 07/26/2022
- Submitted For:
- Jaime Salazar
- Submitted By:
- Enriqueta Zambrano, DRAINAGE DISTRICT
- Department:
- DRAINAGE DISTRICT
CAPTION
Ratification of approved and fully executed Change Order No. 3, in connection with the project "K-07-02 Drain Improvements’’ reflecting an increase of $6,020.00 and Fifteen (15) additional construction calendar days to Contract No. C-HCDD1-21-049-10-19, with Mor-Wil, LLC, as recommended by Project Engineer, B2Z Engineering, LLC
BACKGROUND
Reason for Change Order: Additional Type C Inlet and Riprap not noted on plans.
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Nora Cavazos | 07/22/2022 05:23 PM |
- Form Started By:
- Enriqueta Zambrano
- Started On:
- 07/13/2022 03:38 PM
- Final Approval Date:
- 07/22/2022