1. Final Approval with Financial Guarantee
a. San Martin No. 8 Subdivision- Pct. 1 (GDSS, LLC.) (Mile 9 ½ North Road & Victoria Road)
No. of Lots: 49 Single-Family
Flood Zone: X
Number of Streetlights:8
Filling Stations:6
Drainage: Yes, Drainage will be provided by storm sewer system and detention will be provided by widening the existing drain ditch.
ETJ: Yes, City of Donna.
Water: Yes, provided by North Alamo Water Supply Corporation.
Sewer: Yes, OSSF’S have been escrowed.
Paved: Yes, Mile 9 ½ North Road and 3 internal streets have been paved.
* Final Approval with a cash deposit in the amount of $73,500.00 for (49) OSSF’S
b. La Pamorana Subdivision- Pct. 4 (Alfredo Aaron Cantu) (Rogers Road & Hoehn Drive)
No. of Lots: 2 Single-Family
Flood Zone: X
Number of Streetlights:N/A
Filling Stations:N/A
Drainage: Yes, Drainage will be provided by natural perculation and surface runoff will drain into Rogers Road side ditch.
ETJ: Yes, City of Edinburg.
Water: Yes, provided by Sharyland Water Supply Corporation.
Sewer: Yes, OSSF’S have been escrowed.
Paved: Yes, Rogers Road is paved.
* Final Approval with a cash deposit in the amount of $3,000.00 for (2) OSSF’S
3. Final Approval
a. Las Comadres No. 9 Subdivision- Pct. 3 (Carlos G. Leal Jr.) (Iowa Road & Mile 3 Road)
No. of Lots: 68 Single-Family
Flood Zone: X
Number of Streetlights:15
Filling Stations:7
Drainage: Yes, Drainage will be provided by storm sewer system discharging into an existing HCDD#1 Regional Facility.
ETJ: Yes, City of Peñitas.
Water: Yes, provided by Agua SUD.
Sewer: Yes, OSSF’S have been installed.
Paved: Yes, Iowa Road, El Gorrito Road and 2 internal streets have been paved.
b. Buena Suerte One Subdivision- Pct. 3 (CL3 Properties, LLC.) (Mile 6 Road & Western Road)
No. of Lots: 21 Single-Family
Flood Zone: X
Number of Streetlights:5
Filling Stations:2
Drainage: Yes, Drainage will be provided by storm sewer discharging onto HCDD#1 Regional Facility.
ETJ: Yes, City of Mission.
Water: Yes, provided by Agua SUD.
Sewer: Yes, OSSF’S have been installed.
Paved: Yes, Mile 6 Road and 2 internal streets have been paved.
c. La Marquesa Estates Subdivision- Pct. 4 (Los Vecindades RGV GP., LLC.) (Owassa Road & Alamo Road)
No. of Lots: 29 Single-Family
Flood Zone: B
Number of Streetlights:6
Filling Stations: 3
Drainage: Yes, Drainage will be provided by storm sewer system and detention will be provided by an existing drain ditch.
ETJ: Yes, City of Edinburg.
Water: Yes, provided by North Alamo Water Supply Corporation.
Sewer: Yes, OSSF’S have been installed.
Paved: Yes, Owassa Road and 2 internal streets have been paved.
d. San Pedro Estates Subdivision- Pct. 1 (Heriberto Garcia) (Mile 6 ½ West Road & Mile 6 ½ North Road)
No. of Lots: 16 Single-Family
Flood Zone: X
Number of Streetlights: N/A
Filling Stations:4
Drainage: Yes, Drainage will be provided by natural perculation and surface runoff onto Mile 6 ½ West Road.
ETJ: Yes, City of Weslaco.
Water: Yes, provided by North Alamo Water Supply Corporation.
Sewer: Yes, OSSF’S have been installed.
Paved: Yes, Mile 6 ½ West Road and Mile 6 ½ North Road are paved.
e. Re-Plat of Lot 2 Los Caminos Subdivision- Pct. 4 (Gomer L. Sanchez) (Trenton Road & Alamo Road)
No. of Lots: 2 Single-Family
Flood Zone: B
Number of Streetlights:N/A
Filling Stations:N/A
Drainage: Yes, Drainage will be provided by natural perculation within the proposed lots and surface runoff will drain into Trenton Road side ditch.
ETJ: Yes, City of Edinburg.
Water: Yes, provided by North Alamo Water Supply Corporation.
Sewer: Yes, OSSF’S have been installed.
Paved: Yes, Trenton Road is paved.
f. Cadena Estates Subdivision- Pct. 3 (Juan E. Cadena) (Brushline Road & 3 Mile Road)
No. of Lots: 2 Single-Family
Flood Zone: C
Number of Streetlights:N/A
Filling Stations:N/A
Drainage: Yes, Drainage will be provided by natural perculation and surface runoff will drain into Brushline Road side ditch.
ETJ: Yes, City of Mission.
Water: Yes, provided by Agua SUD.
Sewer: Yes, OSSF’S have been installed.
Paved: Yes, Brushline Road is paved.
g. Ranchito Cortina Subdivision- Pct. 1 (Jose & Alejandra Cortina) (Mile 7 West Road & Mile 21 North Road)
No. of Lots: 1 Single-Family
Flood Zone: X
Number of Streetlights:N/A
Filling Stations:N/A
Drainage: Yes, Drainage will be provided by natural perculation and surface runoff will drain into Mile 7 West Road side ditch.
ETJ: No, Rural area.
Water: Yes, provided by North Alamo Water Supply Corporation.
Sewer: Yes, OSSF has been installed.
Paved: Yes, Mile 7 West Road is paved.
a. San Martin No. 8 Subdivision- Pct. 1 (GDSS, LLC.) (Mile 9 ½ North Road & Victoria Road)
No. of Lots: 49 Single-Family
Flood Zone: X
Number of Streetlights:8
Filling Stations:6
Drainage: Yes, Drainage will be provided by storm sewer system and detention will be provided by widening the existing drain ditch.
ETJ: Yes, City of Donna.
Water: Yes, provided by North Alamo Water Supply Corporation.
Sewer: Yes, OSSF’S have been escrowed.
Paved: Yes, Mile 9 ½ North Road and 3 internal streets have been paved.
* Final Approval with a cash deposit in the amount of $73,500.00 for (49) OSSF’S
b. La Pamorana Subdivision- Pct. 4 (Alfredo Aaron Cantu) (Rogers Road & Hoehn Drive)
No. of Lots: 2 Single-Family
Flood Zone: X
Number of Streetlights:N/A
Filling Stations:N/A
Drainage: Yes, Drainage will be provided by natural perculation and surface runoff will drain into Rogers Road side ditch.
ETJ: Yes, City of Edinburg.
Water: Yes, provided by Sharyland Water Supply Corporation.
Sewer: Yes, OSSF’S have been escrowed.
Paved: Yes, Rogers Road is paved.
* Final Approval with a cash deposit in the amount of $3,000.00 for (2) OSSF’S
3. Final Approval
a. Las Comadres No. 9 Subdivision- Pct. 3 (Carlos G. Leal Jr.) (Iowa Road & Mile 3 Road)
No. of Lots: 68 Single-Family
Flood Zone: X
Number of Streetlights:15
Filling Stations:7
Drainage: Yes, Drainage will be provided by storm sewer system discharging into an existing HCDD#1 Regional Facility.
ETJ: Yes, City of Peñitas.
Water: Yes, provided by Agua SUD.
Sewer: Yes, OSSF’S have been installed.
Paved: Yes, Iowa Road, El Gorrito Road and 2 internal streets have been paved.
b. Buena Suerte One Subdivision- Pct. 3 (CL3 Properties, LLC.) (Mile 6 Road & Western Road)
No. of Lots: 21 Single-Family
Flood Zone: X
Number of Streetlights:5
Filling Stations:2
Drainage: Yes, Drainage will be provided by storm sewer discharging onto HCDD#1 Regional Facility.
ETJ: Yes, City of Mission.
Water: Yes, provided by Agua SUD.
Sewer: Yes, OSSF’S have been installed.
Paved: Yes, Mile 6 Road and 2 internal streets have been paved.
c. La Marquesa Estates Subdivision- Pct. 4 (Los Vecindades RGV GP., LLC.) (Owassa Road & Alamo Road)
No. of Lots: 29 Single-Family
Flood Zone: B
Number of Streetlights:6
Filling Stations: 3
Drainage: Yes, Drainage will be provided by storm sewer system and detention will be provided by an existing drain ditch.
ETJ: Yes, City of Edinburg.
Water: Yes, provided by North Alamo Water Supply Corporation.
Sewer: Yes, OSSF’S have been installed.
Paved: Yes, Owassa Road and 2 internal streets have been paved.
d. San Pedro Estates Subdivision- Pct. 1 (Heriberto Garcia) (Mile 6 ½ West Road & Mile 6 ½ North Road)
No. of Lots: 16 Single-Family
Flood Zone: X
Number of Streetlights: N/A
Filling Stations:4
Drainage: Yes, Drainage will be provided by natural perculation and surface runoff onto Mile 6 ½ West Road.
ETJ: Yes, City of Weslaco.
Water: Yes, provided by North Alamo Water Supply Corporation.
Sewer: Yes, OSSF’S have been installed.
Paved: Yes, Mile 6 ½ West Road and Mile 6 ½ North Road are paved.
e. Re-Plat of Lot 2 Los Caminos Subdivision- Pct. 4 (Gomer L. Sanchez) (Trenton Road & Alamo Road)
No. of Lots: 2 Single-Family
Flood Zone: B
Number of Streetlights:N/A
Filling Stations:N/A
Drainage: Yes, Drainage will be provided by natural perculation within the proposed lots and surface runoff will drain into Trenton Road side ditch.
ETJ: Yes, City of Edinburg.
Water: Yes, provided by North Alamo Water Supply Corporation.
Sewer: Yes, OSSF’S have been installed.
Paved: Yes, Trenton Road is paved.
f. Cadena Estates Subdivision- Pct. 3 (Juan E. Cadena) (Brushline Road & 3 Mile Road)
No. of Lots: 2 Single-Family
Flood Zone: C
Number of Streetlights:N/A
Filling Stations:N/A
Drainage: Yes, Drainage will be provided by natural perculation and surface runoff will drain into Brushline Road side ditch.
ETJ: Yes, City of Mission.
Water: Yes, provided by Agua SUD.
Sewer: Yes, OSSF’S have been installed.
Paved: Yes, Brushline Road is paved.
g. Ranchito Cortina Subdivision- Pct. 1 (Jose & Alejandra Cortina) (Mile 7 West Road & Mile 21 North Road)
No. of Lots: 1 Single-Family
Flood Zone: X
Number of Streetlights:N/A
Filling Stations:N/A
Drainage: Yes, Drainage will be provided by natural perculation and surface runoff will drain into Mile 7 West Road side ditch.
ETJ: No, Rural area.
Water: Yes, provided by North Alamo Water Supply Corporation.
Sewer: Yes, OSSF has been installed.
Paved: Yes, Mile 7 West Road is paved.
BACKGROUND
Fiscal Impact
Attachments
- San Martin #8
- LA PAMORANA SUBD;F
- Las Comadres #9
- Buena Suerte One.; F
- La Marquesa Est.;P
- SAN PEDRO ESTATES;F
- REPLAT OF LOT 2, LOS CAMINOS.;F
- CADENA EST;F
- Ranchito Cortina.; F
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Budget and Management | Veronica Ortiz | 11/09/2022 04:12 PM |
| Final Approval | Monica Salinas | 11/10/2022 05:21 PM |
- Form Started By:
- Flor Castillo
- Started On:
- 11/09/2022 03:58 PM
- Final Approval Date:
- 11/10/2022