AI - 92136
5.G.
DD-REGULAR AGENDA REGULAR MTG
- Meeting Date:
- 08/22/2023
- Submitted For:
- Omar Anzaldua Jr.
- Submitted By:
- Enriqueta Zambrano
- Department:
- DRAINAGE DISTRICT
CAPTION
Acceptance and approval of Work Authorization No. 2 to provide Construction Management and Inspection Services in the total amount of $153,528.47 as submitted by B2Z Engineering, LLC, for "North Main Drain III Storm Water Project Ph I & Ph II'', through Contract No. C-HCDD1-23-036-07-25.
BACKGROUND
For the project North Main Drain III Storm Water Project Ph I & Ph II (PCT 4 ARPA Project)
Phase I total cost $57,805.07
Phase II total cost $95,723.40
B2Z Engineering total cost PH I & PH II $153,528.47
Phase I total cost $57,805.07
Phase II total cost $95,723.40
B2Z Engineering total cost PH I & PH II $153,528.47
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Nora Cavazos | 08/18/2023 04:12 PM |
- Form Started By:
- Enriqueta Zambrano
- Started On:
- 08/17/2023 02:15 PM
- Final Approval Date:
- 08/18/2023