AI - 92704
6.B.
DD-REGULAR AGENDA SPECIAL MTG
- Meeting Date:
- 10/03/2023
- Submitted For:
- Omar Anzaldua Jr.
- Submitted By:
- Enriqueta Zambrano
- Department:
- DRAINAGE DISTRICT
Information
CAPTION
Requesting approval of Change Order No. 1 for an increase in the amount of $98,914.71, and Ninety (90) additional construction calendar days, in connection with the project "Construction of Cast-in-Place Reinforced Concrete Boxes 7' x 7' for Southwest Weslaco - 2018 Bond Referendum Project No. 35'', Contract No. C-HCDD1-23-032-08-08, with Mor-Wil, LLC, as recommended by Project Engineer, Asst. District General Manager, Omar Anzaldua Jr., PE, CFM, PMP, CCM.
BACKGROUND
Project Completion date for CO-1: April 04, 2024
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Nora Cavazos | 09/29/2023 04:27 PM |
- Form Started By:
- Enriqueta Zambrano
- Started On:
- 09/28/2023 09:33 AM
- Final Approval Date:
- 09/29/2023