CAPTION
Ratification of approved and fully executed Change Order No. 1, for the project "Rincon de Encinos Phase III Storm Water Improvements’’ reflecting an increase amount of $32,565.42 and additional Twenty (20) additional construction calendar days to Contract No. C-HCDD1-23-003-08-08, with McAllen Multi Service, as recommended by project engineer, Asst. District General Manager, Omar Anzaldua Jr., PE, CFM, PMP, CCM.
BACKGROUND
Project completion date per CO-1: January 25, 2024