CAPTION
1. Requesting approval of the final negotiated Professional Engineering Services Agreement with SAMES, Inc. in connection with the "West Main Drain III Extension Phase 2 - 2023 Bond Referendum Project No. 14", Contract No. C-HCDD1-23-072-10-31 as approved for negotiations on 09/05/23, AI 92349 (subject to final legal review).
2. Acceptance and approval of Work Authorization No. 1 in the amount of $259,733.19 as submitted by SAMES, Inc. through Contract No. C-HCDD1-23-072-10-31 to provide Professional Engineering Services for "West Main Drain III Extension Phase 2 - 2023 Bond Referendum Project No. 14" (subject to final legal review).
2. Acceptance and approval of Work Authorization No. 1 in the amount of $259,733.19 as submitted by SAMES, Inc. through Contract No. C-HCDD1-23-072-10-31 to provide Professional Engineering Services for "West Main Drain III Extension Phase 2 - 2023 Bond Referendum Project No. 14" (subject to final legal review).
BACKGROUND
Fiscal Impact
Attachments
No file(s) attached.
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Nora Cavazos | 10/27/2023 02:57 PM |
- Form Started By:
- Linda Martinez
- Started On:
- 10/25/2023 03:26 PM
- Final Approval Date:
- 10/27/2023