AI - 93076
6.A.
DD-REGULAR AGENDA SPECIAL MTG
- Meeting Date:
- 10/31/2023
- Submitted By:
- Alvaro Chuc
- Department:
- DRAINAGE DISTRICT
Information
CAPTION
Weslaco Drain - Budget 335
Approval of Application for Payment No. 3 in the amount of $62,697.96 from Mor-Wil, LLC pertaining to construction contract No. C-HCDD1-21-017-R-05-02 Weslaco Drain Additional Box. Project Engineer: Omar Anzaldua, Jr. PE, CFM PO#647867
Approval of Application for Payment No. 3 in the amount of $62,697.96 from Mor-Wil, LLC pertaining to construction contract No. C-HCDD1-21-017-R-05-02 Weslaco Drain Additional Box. Project Engineer: Omar Anzaldua, Jr. PE, CFM PO#647867
BACKGROUND
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Nora Cavazos | 10/27/2023 02:58 PM |
- Form Started By:
- Alvaro Chuc
- Started On:
- 10/26/2023 03:54 PM
- Final Approval Date:
- 10/27/2023